1. Overview
The Electrical Team successfully completed 36 documented tasks for February 2026, covering Preventive Maintenance, Load Balancing, Corrective Repairs, Signage Installation, Satellite Relocation, and other electrical works across multiple branches nationwide.
This report consolidates all activities from:
- PM Records (February 2026)
- 3rd Week of February Weekly Report
- 4th Week of February Weekly Report
2. Summary of Accomplishments
Task Distribution
- Preventive Maintenance: 18
- Load Balancing: 10
- Corrective Repairs: 6
- Signage Works: 4
- Satellite Relocation: 4
- Other Works: 3
3. Branch‑by‑Branch Breakdown
WNE – Waltermart North EDSA
- Preventive Maintenance
- Load balancing performed by transferring high‑load circuits to no‑load circuits.
SSN/168 – Divisoria
- Lighting Preventive Maintenance.
SSV – South Supermarket Valenzuela
- Lighting Preventive Maintenance.
MTR – Montalban Town Center
- Replacement of busted lights.
- Additional downlights required.
PPLP / Pixie – Festival Mall Alabang
- Wiring organization and repair at token booth.
PHH3 – SM Southmall
- Retightening of L2 busbar for mall thermal scan.
- Assisted mall engineering.
PHSI – Antel Main Office
- Replacement of defective emergency lights.
PSLB – SM Lemery Batangas
- Troubleshooting and replacement of defective breaker.
PPL1 XSite – Festival Mall Alabang
- Installation and wiring of Toms World signage.
- Dismantling of old sintra signage and fabrication of new brackets.
SM Marilao
- Replacement of two burned‑out KWHR meters.
PLPP / Pixie Satellite – Festival Mall
- Replacement of busted bulbs.
PL1 XSite – Festival Mall
- Assembly and rectification of signage for Redemption area.
STP – SM Telabastagan
- Electrical inspection for new satellite relocation.
- Awaiting mall approval.
GTP – SM Telabastagan
- Panel board preventive maintenance and load balancing.
PSLP – SM Center Las Piñas
- Replacement of defective dome light sockets and busted lights.
SRL – SM Rosales
- Panel board preventive maintenance and load balancing.
SJB – Starmall San Jose
- Panel board preventive maintenance and load balancing.
PSMU – SM Muntinlupa
- Satellite relocation and electrical works.
- Replacement of busted dome lights.
PPL‑1 – Festival Mall
- Machine relocation and electrical works.
GOC – SM Olongapo
- Panel board preventive maintenance and load balancing.
SOC – SM Olongapo
- Panel board preventive maintenance and load balancing.
SGC – SM Grand
- Dome light repair and ocular inspection.
PSCM – SM Molino
- Replacement of defective 40W panel lights.
- Pending delivery of remaining panel lights.
SSJ – SM San Jose del Monte
- Panel board preventive maintenance and load balancing.
SCT – SM Trece
- Installation and wiring of new satellite.
PEWF – Festival Mall
- Replacement of busted canopy lights.
RNE – Robinsons Novaliches
- Panel board preventive maintenance and load balancing.
SCF – SM Fairview
- Panel board preventive maintenance.
- Unbalanced loads observed.
PSCS – Ever Gotesco Commonwealth
- PM and load balancing for main and satellite.
- Emergency response for tripping breaker and blown LED strip power supply.
4. Weekly Report Highlights
3rd Week of February
- Installation of Toms World signage (PPL1‑X Site).
- Replacement of defective breaker (PSLB).
- Electrical works at PSTH, PRFC, PPLP.
- Replacement of defective emergency light (Antel).
- Electrical materials estimation (PSMU).
4th Week of February
- Preventive Maintenance and Load Balancing across:
- PSRC
- PWCC
- PDAS
- PDGC
- PSTO
- PRTL
- Assembly of fluorescent lights for PPL1 Warehouse.
5. Corrective Repairs Summary
- Breaker replacements (PSLB, PSCS).
- Emergency light replacement (Antel).
- Busted lights and dome lights replaced across multiple branches.
- KWHR meter replacement (SM Marilao).
- Wiring rectification at Pixie Token Booth.
6. Signage & Installation Works
- Toms World signage installation at Festival Mall (PPL1 XSite).
- Dismantling of old signage and fabrication of new brackets.
- Assembly of signage for Redemption area.
- Warehouse fluorescent light assembly.
7. Satellite Relocation Works
- PSMU – Relocation completed.
- PPL‑1 XSite – Machine relocation completed.
- SCT – New satellite installed and wired.
- STP – Awaiting mall approval for relocation.
8. Manpower Involved
Primary personnel:
- Johnny Austria
- Joseph Cristal Jr.
- Jerico Simon
- Petemar Solano
- Ronil Jardio
- Chris Neri
Supported by various mall engineering teams and branch verifiers.
9. Recommendations
- Continue monthly PM to maintain load balance and reduce corrective incidents.
- Standardize grounding checks across all branches.
- Improve supplier coordination for lighting deliveries.
- Maintain inventory of emergency lights, dome lights, and panel lights.
- Pre‑fabricate signage brackets to reduce installation time.
10. Conclusion
February 2026 was a productive month with extensive preventive maintenance, corrective repairs, signage installations, and satellite relocations. The Electrical Team demonstrated strong performance, rapid response to urgent issues, and consistent support for operational requirements across all branches.