END OF JANUARY 2026 ACCOMPLISHMENT REPORT
This report consolidates all Preventive Maintenance, Corrective Works, Electrical Installations, and Technical Activities performed from January 1–31, 2026, based on the PM Records dataset.
1. Preventive Maintenance Activities
Extensive PM work was completed across multiple branches, focusing on panel boards, lighting systems, load balancing, and safety inspections.
Branches with Completed PM (Panel Boards & Load Balancing)
- Waltermart Balayan (PWBB)
- SM Lemery Batangas (PSLB)
- Robinsons Meycauayan (RMC)
- Ever Gotesco Commonwealth (ECO)
- Montalban Town Center (MTR)
- SM Pulilan (SPB)
- SM Baliwag (SBB – Tomsworld, Funhouse, Gotcha)
- Robinsons Antipolo (RAM)
- SM North Caloocan (SNC)
- SM Novaliches (SNQ)
- Waltermart Plaridel (WCP)
- Waltermart San Fernando Pampanga (WMP)
Key PM Outcomes
- All inspected panel boards were tightened, cleaned, and load‑balanced.
- Multiple branches required load redistribution to prevent overheating.
- Several branches flagged burned terminals, defective breakers, or neutral upgrades (see Section 4: Issues Requiring Follow‑Up).
2. Corrective Maintenance & Repairs
Lighting Repairs
- SM Southmall (PHH3)
- Replaced canopy DL and dome lights
- Note: Breaker replacement pending from Muralla
- Ever Gotesco Commonwealth (ECO)
- Replaced 8 of 9 high‑bay fixtures
- Note: 1 fixture defective
- Sir Oliver Residence
- Replaced busted lights
- Installed CCTV power supply
- SM Center Las Piñas (PSLP)
- Replaced defective round LED canopy lights
Convenience Outlet / Baseboard Repairs
- Festival Mall (PPL1, PWEF)
- Replaced defective outlets
- Repaired panel board push‑lock
- Installed new baseboard C.O.
- Antel Corporate Center (Head Office)
- Repaired convenience outlet at Ma’am Raquel’s office
3. Electrical Installations & Upgrades
Panel Board Installations / Terminations
- Tutuban Mall (TCL / PTCL)
- Installed new panel board
- Terminated circuits
- Dismantled old panel boards
- Note: Waiting for main circuit breaker before energization
- Eastwood Mall (EWM)
- Installed panel board, sub‑meter, and convenience outlet
- Conducted ocular for satellite area
Machine Relocation & Power Supply Works
- Festival Mall (PPLP)
- Relocated machine supply
- Additional wiring for Pixie Forest
- SM Molino (PSCM)
- Electrical works and machine relocation completed
4. CCTV Installations & Network Cabling
Completed
- Festival Mall (PLPP / PPLP)
- Additional CCTV wiring
- CAT6 UTP cable installation
- Camera mounting and testing
Ongoing
- Ever Gotesco Commonwealth (ECO)
- Additional CCTV layout and tracing of non‑functional lines
- Status: Ongoing
5. Dismantling & Recovery Works
Tutuban Mall (TCL / PTCL)
- Dismantled downlights, dome lights, and old panel boards
- Pulled out lighting equipment
- Recovered materials for reuse in Funhouse area
- Note: Replacement panel board sourced from old Tomsworld unit
6. Issues Requiring Follow‑Up
These items need further action, materials, or approval:
Outstanding / Pending
- PTCL – Tutuban Mall
- Main circuit breaker late Delivery
- Panel board cannot be energized w/o MCB
- PHH3 – SM Southmall
- Breaker replacement pending from Muralla
- ECO – Ever Gotesco Commonwealth
- One high‑bay fixture defective (Replacement not yet arrived)
- RAX – Robinsons Antipolo
- Main circuit breaker for replacement
- Burned L1/L2 terminals
- Neutral wire requires upgrade
- PPLP – Festival Mall
- CCTV wiring ongoing (due Jan 8)
7. Summary of Workforce Deployment
Primary Electricians
- Jerico Simon
- Petemar Solano
- Chris Neri
- Ronil Jardio
- Johnny Austria
- Joseph Cristal Jr
Work Highlights
- High volume of PM tasks completed
- Multiple corrective works resolved same‑day
- Several installations and dismantling operations executed efficiently
- Strong coordination with mall engineers and branch supervisors
OVERALL JANUARY 2026 PERFORMANCE
January 2026 showed high operational output, with:
- 60+ PM tasks completed
- 20+ corrective repairs
- Multiple installations and dismantling operations
- Ongoing CCTV and electrical upgrades
- Several issues identified early, preventing equipment failure
The team demonstrated excellent responsiveness, technical accuracy, and consistent safety compliance across all branches.