4th Week of March 2026

 Summary of Activities (March 23–31, 2026)
  1. Emergency & Corrective Works
  • SM Muntinlupa (PSMU)
    • Responded to an urgent call due to a breaker tripping caused by shorted wiring.
      “There was an ungent call at smu because the breaker supplying the machines tripped due to shorted wiring.”
    • Conducted rectification and rewiring of defective baseboard wires.
      “RECTIFICATION and RE-WIRING DEFECTIVE WIRE . IN BASEBOARD PSMU”
    • Addressed an emergency caused by rats chewing baseboard wires, damaging insulation and causing breaker trips.
      “Rats chewed the baseboard wires, damaging the insulation, which may be causing the breaker to trip.”
  • SM Grand Central (SGC)
  • Repaired defective floor outlet.
  1. Preventive Maintenance & Load Balancing
  • Evia Mall Daanghari (PEVL)
    • Preventive maintenance and load balancing of panel board.
      “Preventive Maintenance and Load balancing pevl”
  • Puregold Marikina (PYM)
    • Preventive maintenance on panel board; MDP main breaker restored to normal condition.
  • SM Downtown Antipolo (CAM)
    • Preventive maintenance with load balancing.
  • PPL1 – Festival Mall Alabang
    • Relocation of machine and load balancing.
      “Relocation of Machine ppl1 and Load balancing”
  • PWQE – Waltermart Bicutan
  • Replaced defective pilot lights and performed electrical works.
  1. Relocation & Rewiring Works
  • PWBB – Waltermart Balayan
    • Relocation of panel board breaker and rewiring.
      “Relocation of panel board breaker pwbb”
  • PPL1 X-Site
  • Multiple tasks including electrical works, load balancing, and machine relocation.
  1. Ocular Inspections & Coordination
  • SM City BF Parañaque (PSBQ)
    • Ocular and coordination with mall admin for new satellite proposal.
  • SM Lipa Batangas
    • Ocular inspection and coordination for new satellite area.
      “Ocular and coordinate mall admin new satellite area sm lipa”
  • SM Nova (SNQ)
  • Ocular inspection for dismantling and later dismantling of area, with recovered materials properly surrendered.
  1. Other Technical Tasks
  • Installation of body ground on machine to eliminate grounding issues.
    “INSTALLATION A BODY GROUND ON THE MACHINE TO ELIMINATE THE GROUNDING ISSUE”
  • General electrical works across multiple sites (PWQE, PWBB, PPL1).
Overall Summary
Across the 4th week of March 2026, the electrical team completed 13 documented tasks, including:
  • Emergency repairs (shorted wiring, rat-damaged wires, tripping breakers)
  • Preventive maintenance on multiple branches
  • Load balancing and panel board servicing
  • Machine and panel board relocation
  • Ocular inspections for dismantling and new satellite proposals
  • Grounding installation to resolve machine grounding issues
All tasks were completed successfully except for ongoing coordination at SM Lipa Batangas.