ELECTRICAL WEEKLY SUMMARY REPORT
1st & 2nd Week of April 2026
1. OVERALL SUMMARY
Across both weeks (April 1–15, 2026), the Electrical Team completed 39 documented activities covering:
- Preventive Maintenance (PM)
- Load Balancing
- Breaker Replacement / Retightening
- Machine Relocation
- Lighting Repairs
- CCTV Wiring Rectification
- Transformer Preventive Maintenance
- Electrical Safety Certification
- Outlet and Baseboard Repairs
- Preparation of Electrical Materials for New Satellite Sites
All tasks were marked OK / Completed, with no unresolved issues reported.
2. KEY ACTIVITIES PERFORMED
A. Preventive Maintenance (Majority of Tasks)
PM activities were performed across multiple branches including:
- TOMSWORLD
- Funhouse
- Pambi Corp
- Joy Planet Inc
- Gotcha Prize
- Jack’s Adventure
Common PM findings and actions:
- Load balancing of LP/PP panels Example from record: “LP/PP is unbalance (L1-26A, L2-12A, L3-15A)… After balancing: L1-17.2A, L2-17.5A, L3-18.2A.”
- Cleaning of panel boards
- Retightening of terminals and busbars
- Correction of loose or overheated terminals (yellow tag thermal scan)
B. Load Balancing
Load balancing was repeatedly required due to:
- Aircon units causing uneven loads
- Additional lighting wattage
- Multiple ACCUs in some branches
- Old breakers overheating under unbalanced loads
Branches with load balancing activities include:
- SM Baliwag
- SM San Jose del Monte
- SM Pulilan
- SM East Ortigas
- Festival Mall Alabang
- Southmall Las Piñas
- Puregold Taguig
- Eastwood
C. Breaker Replacement / Retightening
Several branches required breaker replacement due to:
- Age (some breakers in use since 2008)
- Burned-out terminals
- Overloading
- Mechanical wear
Branches
- Montalban Town Center – multiple 20A breakers replaced
- SM Fairview – installation of new breaker
- SM Pulilan – retightening of breaker terminals
D. Machine Relocation + PM + Load Balancing
Performed for:
- PPH3 (Southmall Las Piñas)
- PSCS (SM Sucat)
- PWQE (Waltermart Bicutan)
These activities included:
- Relocating machines
- Rebalancing loads
- Correcting burned or loose wires
- Conducting full PM after relocation
E. Lighting Works
- Replacement of busted lights at PPLP, Tempo 2, Montalban Town Center, and Festival Mall Alabang
- Downlight replacement
- Dome light replacement
F. CCTV & Wiring Rectification
- PPLP – Festival Mall Alabang Rectification of CCTV UTP cable and internet wiring.
G. Transformer Preventive Maintenance
Performed at:
- PPL1 – Xsite Festival Mall Alabang
- PPLP – Pixie Festival Mall Alabang
Activities included:
- Inspection
- Cleaning
- Load check
- Terminal tightening
H. Electrical Safety Certification
Issued for:
- Funhouse – Morong CenterPoint
- Funhouse – Tanay Town Center
Both passed with Status: OK.
I. Outlet / Baseboard Repairs
- Ever Commonwealth – floor outlet repair
- Festival Mall Alabang (PEWF) – defective baseboard outlet replacement
J. New Satellite Preparation
- PPLP – Festival Mall Alabang Preparation and assembly of panel board
- SM Lipa Batangas Ocular inspection and coordination with mall admin for new satellite site
3. HIGHLIGHTS for 2nd Week of April
The PPT emphasizes visual documentation of:
- Replacement of defective lights (Tempo 2 – Pixie)
- Preventive maintenance and load balancing at PSTH, PPH3, PSCS, PWQE
- Rectification of CCTV wiring at PPLP
- Transformer PM at PPL1 and PPLP
- Assembly of new panel board for PPLP
These align with the PDF records and confirm successful completion of all tasks.
4. GENERAL OBSERVATIONS
- Load imbalance remains the most common recurring issue across branches.
- Old breakers (2008–2020) frequently require replacement due to wear and overheating.
- Aircon units are a major contributor to load imbalance.
- Thermal scanning continues to be effective in identifying hotspots early.
- Multiple branches required machine relocation followed by PM and load balancing.
- No major electrical failures were reported during the period.
5. RECOMMENDATIONS
- Schedule periodic thermal scanning for branches with repeated yellow-tag findings.
- Replace aging breakers proactively, especially those older than 10 years.
- Standardize load distribution guidelines for branches with multiple ACCUs.
- Continue PM + load balancing combo for branches undergoing machine relocation.
- Maintain documentation with photos for audit and compliance.