SUMMARY – ELECTRICAL WEEKLY REPORT (2nd Week of January 2026)
1. General Overview
Electrical teams from TW–DCD Department completed multiple tasks across PPL1‑XSite, PSCM, PSLP, and PEWF areas. Activities mainly involved electrical installation, relocation, repair, and preventive maintenance works.
2. Machine Relocation Works (PPLP / PPL1‑XSite)
- Conducted electrical disconnection and reconnection to support the relocation of machines.
- Installed or rearranged conduits, wiring, and cable supports to match new machine positions.
- Ensured proper grounding and safe energization after relocation.
3. Replacement of Defective Outlets & Push‑Lock Components
(Outlet & Panelboard‑Related Images Included)
- Replaced defective outlets, ensuring safe power delivery to equipment.
- Changed faulty push‑lock switches mounted on the panelboard at PEWF.
- Verified outlet integrity and proper load conditions after replacement.
4. Preventive Maintenance – Panelboard
Preventive maintenance (PM) was performed on selected panelboards, which included:
- Tightening of terminal lugs to avoid overheating.
- Cleaning dust accumulation inside the panelboard enclosure.
- Checking breakers for proper mechanical operation.
- Inspecting for signs of carbonization, burnt marks, or loose contacts.
- Replacing defective push‑lock units and related components as needed.
These PM activities improved reliability, reduced electrical risks, and helped ensure continuity of operations.
5. Other Electrical Works (Across Multiple Sites)
PPL1‑XSite
- Electrical routing, conduit installation, and power line adjustments.
- Support activities for machine setup and testing.
PSCM
- Conducted inspection and installation tasks; supported ongoing electrical upgrades.
PEWF
- Additional electrical improvements and minor corrections to existing installations.
PSLP
- Wiring corrections and panel checks; supported area equipment electrical requirements.