Annual Report
1. Electrical Installations & Store Enhancements
- Smart LED installation and wiring optimization for Tomsworld SM Molino
- Revised wiring diagrams to reduce voltage drop
- Installation and replacement of high‑bay dome lights (Ever Gotesco Commonwealth)
- Installation of extensions and additional lighting for multiple branches
- Construction and electrical setup of SM Novaliches Tempo Area
- Relocation and installation of LED downlights (SM Telabastagan)
2. Electrical Plans, Load Computations & Technical Drawings
Completed electrical plans and as‑built revisions for:
- SM East Ortigas Expansion
- Funhouse Tanay Town Center
- Tomsworld SM Novaliches
- Tomsworld SM Lucena
- Tomsworld Iloilo Market Mall
- Tomsworld Gaisano Liloan
- Robinsons Place Tacloban (As‑built & Proposed)
- 168 Mall Divisoria (Proposed & Revised Plans)
- SM Megamall Satellite Area
- Funhouse Puregold QI Central
- TW SM Lucena (BOM & Cost Estimate)
Additional technical outputs:
- Load consumption computation for SM Palawan
- Updated electrical forms (Load Balancing, Megger Test, PM Checklist)
3. Preventive Maintenance (Nationwide)
Successful PM activities across North, Central, South, Visayas, and Mindanao clusters, including:
- SM San Jose, Starmall San Jose, EB Town Center
- SM Fairview, Robinsons Nova, Montalban Town Center
- SM North Caloocan, Waltermart North Edsa
- SM East Ortigas, Robinsons Cainta, Tanay Town Center
- SM Fairview, SM Baliuag, SM Pulilan, Waltermart Plaridel
- Robinsons Cabanatuan, SM Cabanatuan, Robinsons Gapan
- Robinsons Angeles, SM Pampanga, Waltermart San Fernando
- SM Tarlac, SM Rosales, Robinsons Ilocos, Puregold Ilocos
- SM Tuguegarao, Robinsons Tuguegarao
- SM Daet, SM Sorsogon, SM Legazpi, LCC Legazpi
- Festival Mall (Pixie), SM Muntinlupa
- SM Bacoor, SM Dasmariñas, Waltermart Carmona
- Robinsons Imus, Waltermart Dasmariñas
- SM Center Molino, RFC Mall, SM Southmall
- SM Las Piñas, SM Sucat
- SM Iloilo, SM Roxas, SM Seaside Cebu, SM Cebu
- Gaisano Masbate, LCC Masbate
- SM Palawan, Robinsons Palawan
- Robinsons North Tacloban, Robinsons Marasbaras
- SM Davao, Robinsons Iligan, Robinsons Butuan, Gaisano Surigao
4. Emergency Electrical Works & Troubleshooting
Completed urgent responses for:
- Short circuit repair at SM Mall of Asia
- Power‑on delay troubleshooting at Funhouse Montalban
- Circuit breaker replacement and repairs (multiple branches)
- Floor outlet troubleshooting at SM Mall of Asia
- Electrical insulation checks due to water leaks (Tutuban Center Mall)
- Emergency power supply repairs at SM Pampanga
- Machine relocation and load balancing for various branches
5. CCTV Installations & Upgrades
- Roughing‑ins and BOM preparation for Funhouse Taguig
- CCTV installation for Pixie
- Ocular inspections and BOM for CCTV upgrades (SM San Lazaro, Ever Gotesco Commonwealth)
- Installation of new CAT6 cables for CCTV upgrades
6. Smart LED / ESP32 Development & Automation
Completed firmware and software development:
- Refactoring WLED v14.4 for ESP32 memory optimization
- ESP32 reset code creation and testing
- Firmware updates: V15.1, V16.0, V16.1, V16.1b, V16.2
- Added features: PST timezone, blend modes, sound‑reactive effects
- Development of TWLED/WLED GUI using AI
- Creation of Project Tracker Web App
- Creation of Preventive Maintenance Web App (launched on GitHub + Firebase)
7. Ocular Inspections & Site Assessments
- Multiple site inspections for electrical provisions, LED measurements, CCTV routing, and demolition assessments
- Coordination with mall engineering teams for compliance and safety
- Verification of panel board conditions based on thermography reports
8. Machine Relocation & Load Balancing
- Full load tests and load distribution for SM Novaliches
- Machine relocation and load balancing across multiple Luzon branches
- Ensured compliance with PEC standards and operational safety