3rd week of March 2026 Report

Electrical Weekly Report Summary

3rd Week of March 2026 (March 15–22)

TW‑DCD Department – Johnny Austria & Joseph Cristal Jr.

🛠️ Overall Scope of Work

Across the week, the team completed 15 documented tasks involving:

  • Preventive Maintenance (PM)
  • Load Balancing
  • Electrical Works
  • Breaker Replacement
  • Dismantling and Pull‑out of Electrical Connections

Most activities focused on panel boards, with some work on lighting and CCTV installation.

All tasks were marked OK, with no pending issues reported.

📍 Key Activities by Category

🔧 1. Preventive Maintenance & Load Balancing

Performed repeatedly across multiple branches:

  • PSMU – SM Muntinlupa
    “PREVENTIVE MAINTENANCE AND LOAD BALANCING PSMU”
  • PRGS – Robinsons Galleria South, San Pedro Laguna
    “Preventive Maintenance and Load balancing ”
  • PSIM – SM Center Imus
    “Preventive Maintnance and Load Balancing.”
  • PWDC – Waltermart Dasmariñas
    “Preventive Maintenance and Load balancing”
  • PPL‑1 – Xsite Festival Mall Alabang
    “Preventive Maintenance and Load Balancing”
  • PEWF – East West Festival Mall Alabang
    “Preventive Maintenance and Load balancing”

🔌 2. Electrical Works

  • PPL1 X‑Site EE Room 32R – Electrical works + PM
  • PPL1 X‑Site – Load balancing
  • PRFC – Electrical PM and load balancing
  • General electrical works across multiple branches as shown in the PPT.

🔧 3. Corrective Maintenance

  • RSP – Robinsons Starmill Pampanga
    “2 defective breakers replaced” on March 19.
    Another visit on March 17 noted defective breakers needing replacement.

🛠️ 4. Additional Works

  • MSP – Funhouse
    Installation of additional CCTV camera.
    “ADDIONAL CCTV CAMERA AT MSP”

🏗️ 5. Dismantling & Pull‑Out

  • PSPD – SM San Pedro
    “Dismantled Electrical Supply PSPD satellite… and pullout electrical.”
    “DISMANTLED ELECTRICAL CONNECTIONS AND PULLED OUT THE MACHINES FROM THE PSPD SATELLITE.”

👥 Personnel Involved

Primary team for TW‑DCD:

  • Johnny Austria
  • Joseph Cristal Jr.

Other teams handled additional branches:

  • Chris Neri / Ronil Jardio
  • Jerico Simon / Petemar Solano

All tasks were verified by respective branch representatives.

Overall Assessment

The week shows consistent preventive maintenance coverage, successful load balancing, and timely corrective actions. All branches serviced were left in operational condition, with no unresolved issues reported.

 